U.B.A No 6 Oraifite road, Nnewi, Anambra state.

 

 

 

Client: UBA 

Project Duration:

July 2017 To July 2017

Narration:

Engineering Safety Investigation conducted on the Three (3) level bank building, sequel to the observation of;

  • Settlement of two (2) columns located within banking hall,
  • Shear Cracks were observed on two-floor beams across the banking hall,
  • Rainwater ingress into second-floor toilets & corridors from the cover slab at the rear.

Report of the investigation concluded that;

  • The Two (2) No structural columns are repaired, together with their footings,
  • The Two (2) No Structural beams across the banking hall be repaired outrightly,
  • The cover slab & its support system be Retrofitted to prevent moisture ingress (through grouting, the introduction of parapet walls & drain pipe),